Trapac Container Crane Modifications & Realignment
Location: Jacksonville, FL
Client: Trapac
Project: Crane Modification and Realignment
The crane modifications consisted of the following:
-
Raising two cranes 20 feet (6.1 meters) and extended their booms so the cranes could handle one additional container on vessels
-
Replacing the trolley rails on three cranes
-
Skidding back four cranes for realignment along the dock

Container crane raised 20 feet (6.1 meters) ready for new leg sections



Lifting Frame stored between crane raises

Trolley rails being replaced using GRT Specialized platform that rolls along existing rails while replacing the existing rails with new rail.