South Carolina Ports Authority

 

Under Bridge 001                                                                    Container Crane passing under Don N. Holt Bridge

CRANE RELOCATION, LOW BRIDGE BETWEEN TWO DOCKS

Location:         Charleston, South Carolina

Client:              South Carolina Ports Authority (SCPA)

Project:            Relocate (3) cranes from Wando Welsh Terminal to North Charleston Container Terminal.  Demolish (1) Container Crane at Columbus                           Street Terminal and Demolish (3) Cranes at North Charleston Terminal  

DJI000321st Crane upper assembly Lowered, loaded onto the barge and ready for transit to North Charleston Container Terminal

IHI 1

Demolition of IHI Container Crane at North Charleston Container Terminal